Traffic Alert: 05/29/18

The new ramp access to Chosin Few Way has been opened, providing a direct link from Interchange 14A to the Peninsula.  Additionally, the new Interchange Ramp to southbound Route 440 is open providing a direct connection from Interchange 14A to southbound Route 440. Similarly, vehicles traveling from the Port area to southbound Route 440 can access the new ramp from Port Jersey Boulevard. Please review the traffic flow in the following graphics:

05/25/18: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering the Turnpike) renovation of existing Toll Utility Building continues.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • No work planned.
Avenue E / Proposed Roundabout
  • During the week of 05/27/18, daytime lane closures will be utilized for clean up work between 53rd Street and 50th Street. This work will be supported by Bayonne Police as needed.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited.
Route 440 and Pulaski Street Intersection / Jughandle
  • Continue traffic signal construction on Route 440.
Ramp Area East of Route 440
  • Continue traffic signal construction on Port Jersey Boulevard.

May 21, 2018: 14A Ribbon-Cutting Ceremony

New Jersey Turnpike Authority officials were joined by Governor Phil Murphy, Bayonne Mayor Jimmy Davis, Turnpike Authority Executive Director John Keller, Acting Transportation Commissioner Gutierrez-Scaccetti and many other leaders, construction crew members and press on one of the new ramps on May 21, 2018, for a ceremony to mark the completion of construction on the Interchange 14A Improvement Project. Please CLICK HERE to read the full release.

Traffic Alert: 05/21/18

On Monday, 05/21/18, the new ramp access to Chosin Few Way will open, providing a direct link from Interchange 14A to the Peninsula.  Additionally, the new Interchange Ramp to southbound Route 440 will open providing a direct connection from Interchange 14A to southbound Route 440. Similarly, vehicles traveling from the Port area to southbound Route 440 will access the new ramp from Port Jersey Boulevard. Please review the traffic flow in the following graphics:

05/18/18: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering the Turnpike) renovation of existing Toll Utility Building continues.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • No work planned.
Avenue E / Proposed Roundabout
  • During the week of 05/21/18, daytime lane closures will be utilized for clean up work between 53rd Street and 50th Street. This work will be supported by Bayonne Police as needed.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited.
Route 440 and Pulaski Street Intersection / Jughandle
  • Continue traffic signal construction on Route 440.
Ramp Area East of Route 440
  • Continue traffic signal construction on Port Jersey Boulevard.

05/11/18: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering the Turnpike) renovation of existing Toll Utility Building continues.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • No work planned.
Avenue E / Proposed Roundabout
  • During the week of 05/14/18 through 05/21/18, daytime lane closures will be utilized for clean up work between 53rd Street and 50th Street. This work will be supported by Bayonne Police as needed.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited.
Route 440 and Pulaski Street Intersection / Jughandle
  • Continue traffic signal construction on Route 440.
Ramp Area East of Route 440
  • Continue traffic signal construction on Port Jersey Boulevard.

05/04/18: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering the Turnpike) renovation of existing Toll Utility Building continues.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • No work planned.
Avenue E / Proposed Roundabout
  • During the week of 05/07/18 through 05/21/18, daytime lane closures will be utilized for clean up work between 53rd Street and 50th Street. This work will be supported by Bayonne Police as needed.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited.
Route 440 and Pulaski Street Intersection / Jughandle
  • Continue traffic signal construction on Route 440.
  • During the week of 05/07/18 through 05/21/18, nighttime nighttime lane closures will be utilized for clean up work within the Jughandle and on 440. This work will be supported by Bayonne Police as needed.
Ramp Area East of Route 440
  • Continue traffic signal construction on Port Jersey Boulevard.
  • During the week of 05/07/18 through 05/21/18, clean up work will continue. This work will be supported by Bayonne Police as needed.