Traffic Alert: February 27, 2018

On Tuesday, 02/27/18, northbound and southbound Route 440 at Pulaski Street will be reduced to a single travel lane in each direction.
In addition, westbound Pulaski Street will be reduced to a single travel lane between Pulaski Lane West and Route 440 to accommodate signal work and lane striping.
This work will take place between 9:00AM to 2:00PM and will be supported by Bayonne Police.

02/23/18: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • No work planned.
Avenue E / Proposed Roundabout
  • Continue new roadway construction on the Roundabout of Avenue E, from 52nd Street to 51st Street.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited.
Route 440 and Pulaski Street Intersection / Jughandle
  • Continue traffic signal construction on Route 440.
Ramp Area East of Route 440
  • Continue traffic signal construction on Port Jersey Boulevard.
  • During the week of 03/12/18, daytime hours, asphalt paving operations will resume.

02/16/18: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • A new traffic pattern has been implemented on the new Connector Bridge that provides two travel lanes in each direction. Please CLICK HERE for more information.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • No work planned.
Avenue E / Proposed Roundabout
  • New roadway construction continues on the west side and east side of Avenue E, from 52nd Street to 51st Street.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited.
Route 440 and Pulaski Street Intersection / Jughandle
  • Continue traffic signal construction on Route 440.

Ramp Area East of Route 440

  • Continue roadway widening work on Port Jersey Boulevard.

02/09/18: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • A new traffic pattern has been implemented on the new Connector Bridge that provides two travel lanes in each direction. Please CLICK HERE for more information.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • No work planned.
Avenue E / Proposed Roundabout
  • New roadway construction continues on the west side and east side of Avenue E, from 52nd Street to 51st Street.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited.
Route 440 and Pulaski Street Intersection / Jughandle
  • Continue traffic signal construction on Route 440.

Ramp Area East of Route 440

  • Continue roadway widening work on Port Jersey Boulevard.

02/02/18: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • A new traffic pattern has been implemented on the new Connector Bridge that provides two travel lanes in each direction. Please CLICK HERE for more information.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • No work planned.
Avenue E / Proposed Roundabout
  • New roadway construction continues on the west side and east side of Avenue E, from 52nd Street to 51st Street.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited.
Route 440 and Pulaski Street Intersection / Jughandle
  • Continue traffic signal construction on Route 440.

Ramp Area East of Route 440

  • Continue roadway widening work on Port Jersey Boulevard.