05/19/17: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • Widening construction on the ramps to and from the westbound and eastbound HCE is complete to the extent possible and the final alignment has been implemented. Asphalt resurfacing of the ramps will be performed in 2017.
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the Spring of 2017. This work will be supported by Jersey City and Bayonne Police as needed.
Avenue E / Proposed Roundabout
  • New roadway construction on Avenue E near 53rd Street continues.
  • New bridge pier construction in dedicated work zones continues.
  • Northbound Avenue E was shifted into a new temporary alignment between 50th Street and 51st Street. Please CLICK HERE for more information and graphic.
  • During the week of 06/12/17, nighttime detours of northbound Avenue E, 50th Street to 52nd Street, will be required for approximately one (1) week in support of bridge steel erection. Work will be supported by Bayonne Police.

Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
Route 440 and Pulaski Street Intersection / Jughandle
  • Ramp roadway construction continues.
  • Ramp structure construction to southbound Route 440 continues.
  • Northbound Route 440 reconstruction north of Pulaski Street continues.
Ramp Area East of Route 440
  • New ramp construction continues.
  • Retaining wall construction continues.
  • Bridge deck construction on the bridge structure over Pulaski Street continues.
  • In early-July 2017, nighttime detours of the Pulaski Street Jughandle will be required for approximately one (1) week in support of bridge steel erection. Work will be supported by Bayonne Police.

05/12/17: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • Widening construction on the ramps to and from the westbound and eastbound HCE is complete to the extent possible and the final alignment has been implemented. Asphalt resurfacing of the ramps will be performed in 2017.
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the Spring of 2017. This work will be supported by Jersey City and Bayonne Police as needed.
Avenue E / Proposed Roundabout
  • New roadway construction on Avenue E near 53rd Street continues.
  • New bridge pier construction in dedicated work zones continues.
  • Northbound Avenue E was shifted into a new temporary alignment between 50th Street and 51st Street. Please CLICK HERE for more information and graphic.

  • In mid-June 2017, nighttime detours of northbound Avenue E, 50th Street to 52nd Street, will be required for approximately one (1) week in support of bridge steel erection. Work will be supported by Bayonne Police.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
Route 440 and Pulaski Street Intersection / Jughandle
  • Ramp roadway construction continues.
  • Ramp structure construction to southbound Route 440 continues.
  • Northbound Route 440 reconstruction north of Pulaski Street continues.
Ramp Area East of Route 440
  • New ramp construction continues.
  • Retaining wall construction continues.
  • Bridge deck construction on the bridge structure over Pulaski Street continues.
  • In late-June 2017, nighttime detours of the Pulaski Street Jughandle will be required for approximately one (1) week in support of bridge steel erection. Work will be supported by Bayonne Police.

05/05/17: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • Widening construction on the ramps to and from the westbound and eastbound HCE is complete to the extent possible and the final alignment has been implemented. Asphalt resurfacing of the ramps will be performed in 2017.
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the Spring of 2017. This work will be supported by Jersey City and Bayonne Police as needed.
  • During the week of 05/08/17, nighttime single lane closures will be used on westbound Hudson County Extension, 9:00PM to 4:00AM, to install new signs and sign structures.
Avenue E / Proposed Roundabout
  • New roadway construction on Avenue E near 53rd Street continues.
  • New bridge pier construction in dedicated work zones continues.
  • During the week of 05/08/17, northbound Avenue E will be shifted right to a new temporary alignment between 50th Street and 51st Street. This new alignment will be in place for several months.
  • In mid-June 2017, nighttime detours of northbound Avenue E, 50th Street to 52nd Street, will be required for approximately one (1) week in support of bridge steel erection. Work will be supported by Bayonne Police.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
  • During the weekends of 05/06/17 and 05/12/17, NJ Transit Light Rail Service between 34th Street Station in Bayonne and Danforth Avenue Station in Jersey City will be maintained via NJ Transit bus service, 3:00AM Saturday morning through 3:00AM Monday morning. During this period, bridge structural steel will be erected over the NJ Transit and Conrail train tracks. Please CLICK HERE for more information.
Route 440 and Pulaski Street Intersection / Jughandle
  • Ramp roadway construction continues.
  • Ramp structure construction to southbound Route 440 continues.
  • Northbound Route 440 reconstruction north of Pulaski Street continues.
Ramp Area East of Route 440
  • New ramp construction continues.
  • Retaining wall construction continues.
  • Bridge deck construction on the bridge structure over Pulaski Street continues.
  • In late-June 2017, nighttime detours of the Pulaski Street Jughandle will be required for approximately one (1) week in support of bridge steel erection. Work will be supported by Bayonne Police.

04/28/17: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • Widening construction on the ramps to and from the westbound and eastbound HCE is complete to the extent possible and the final alignment has been implemented. Asphalt resurfacing of the ramps will be performed in 2017.
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the Spring of 2017. This work will be supported by Jersey City and Bayonne Police as needed.
Avenue E / Proposed Roundabout
  • New roadway construction on Avenue E near 53rd Street continues.
  • New bridge pier construction in dedicated work zones continues.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
  • During the weekend of 05/05/17 and 05/12/17, new bridge steel installation operations will be performed over NJ Transit’s Hudson-Bergen Light Rail and Conrail’s Industrial Track. During these periods, NJ Transit Light Rail service between 34th Street Station in Bayonne and Danforth Avenue Station in Jersey City will be maintained via NJ Transit bus service.
Route 440 and Pulaski Street Intersection / Jughandle
  • Ramp roadway construction continues.
  • Median barrier construction on Route 440 continues.
  • Ramp structure construction to southbound Route 440 continues.
  • On Friday, 04/28/17, during the daytime, southbound Route 440 travel lanes will be shifted left along the median barrier and a work zone created on the right (outside shoulder) between Route 185 and Pulaski Street.  On Friday evening, 04/28/17, 8:00PM to 4:00AM) northbound Route 440 travel lanes will be shifted left along the median barrier between Pulaski Street and Harbor Drive.  The northbound Route 440 Ramp to the Turnpike will be maintained on the far right (outside).

Ramp Area East of Route 440
  • New ramp construction continues.
  • Retaining wall construction continues.
  • Bridge deck construction on the bridge structure over Pulaski Street continues.

04/21/17: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • During the weekend of 04/21/17, from 9:00PM Friday through 1:00PM Saturday, asphalt paving construction work will be performed in Toll Lanes 3 & 4 after traffic passes through the Toll Plaza heading towards the Hudson County Extension. Traffic will be split before the Toll Plaza and motorists will need to choose to stay right for the eastbound extension (JC/NYC)  or to the left for the westbound extension (Newark) before passing through the Toll Plaza. Once traffic passes through the Toll Plaza, motorists will not be able to switch lanes. A VMS sign will be placed at Toll Lanes 3 & 4 to direct traffic left and right. Work will be supported by Bayonne and State Police.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • Widening construction on the ramps to and from the westbound and eastbound HCE is complete to the extent possible and the final alignment has been implemented. Asphalt resurfacing of the ramps will be performed in 2017.
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the Spring of 2017. This work will be supported by Jersey City and Bayonne Police as needed.
Avenue E / Proposed Roundabout
  • New roadway construction on Avenue E near 53rd Street continues.
  • New bridge pier construction in dedicated work zones continues.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
  • During the weekend of 05/05/17 and 05/12/17, new bridge steel installation operations will be performed over NJ Transit’s Hudson-Bergen Light Rail and Conrail’s Industrial Track. During these periods, NJ Transit Light Rail service between 34th Street Station in Bayonne and Danforth Avenue Station in Jersey City will be maintained via NJ Transit bus service.
Route 440 and Pulaski Street Intersection / Jughandle
  • Ramp roadway construction continues.
  • Median barrier construction on Route 440 continues.
  • Ramp structure construction to southbound Route 440 continues.
  • During the week of 04/24/17, northbound Route 440 traffic will be shifted left (two northbound lanes adjacent to median) and a work zone will be established on the right.
Ramp Area East of Route 440
  • New ramp construction continues.
  • Retaining wall construction continues.
  • Bridge deck construction on the bridge structure over Pulaski Street continues.
  • During the weekend of 04/21/17, roadway and asphalt paving construction will be performed at the Port Jersey Boulevard intersection at the ramp to northbound Route 440.  All eastbound traffic from the Turnpike to Port Jersey Boulevard (and the Port Marine Terminals) will be directed to Pulaski Street and all westbound traffic from Port Jersey Boulevard will be directed to Route 440 and the Turnpike Ramp via Pulaski Street. Work will be supported by Bayonne Police.

04/14/17: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • During the weekend of 04/21/17, concrete pavement construction will be performed in Toll Lane 8 upon exiting the Turnpike and asphalt pavement construction will be performed in Toll Lanes 3 & 4 upon entering the Turnpike. This work will be supported by Bayonne and the NJ State Police.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • Widening construction on the ramps to and from the westbound and eastbound HCE is complete to the extent possible and the final alignment has been implemented. Asphalt resurfacing of the ramps will be performed in 2017.
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the Spring of 2017. This work will be supported by Jersey City and Bayonne Police as needed.
Avenue E / Proposed Roundabout
  • New roadway construction on Avenue E near 53rd Street continues.
  • Deep bridge foundation construction in dedicated work zones continues. This work will be supported by Bayonne Police as needed.
  • New bridge pier construction in dedicated work zones continues.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
  • During the weekend of 05/05/17 and 05/12/17, new bridge steel installation operations will be performed over NJ Transit’s Hudson-Bergen Light Rail and Conrail’s Industrial Track. During these periods, NJ Transit Light Rail service between 34th Street Station in Bayonne and Danforth Avenue Station in Jersey City will be maintained via NJ Transit bus service.
Route 440 and Pulaski Street Intersection / Jughandle
  • Ramp roadway construction continues.
  • Median barrier construction on Route 440 continues.
  • Ramp structure construction to southbound Route 440 continues.
  • During the week of 04/24/17, northbound Route 440 traffic will be shifted left (two northbound lanes adjacent to median) and a work zone will be established on the right.
Ramp Area East of Route 440
  • New ramp construction continues.
  • Retaining wall construction continues.
  • Bridge deck construction on the bridge structure over Pulaski Street continues.
  • Roadway construction continues.

04/07/17: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • Reconstruction of Toll Lanes 8-10 continues.
  • During the weekend of 04/07/17, concrete pavement construction will be performed in Toll Lanes 8, 9 & 10. At the end of this weekend, Toll Lanes 8, 9 & 10 will be reopened. This work will be supported by Bayonne and the NJ State Police.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • Widening construction on the ramps to and from the westbound and eastbound HCE is complete to the extent possible and the final alignment has been implemented. Asphalt resurfacing of the ramps will be performed in 2017.
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the Spring of 2017. This work will be supported by Jersey City and Bayonne Police as needed.
Avenue E / Proposed Roundabout
  • New roadway construction on Avenue E near 53rd Street continues.
  • Deep bridge foundation construction in dedicated work zones continues. This work will be supported by Bayonne Police as needed.
  • New bridge pier construction in dedicated work zones continues.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
  • During the weekend of 05/05/17 and 05/12/17, new bridge steel installation operations will be performed over NJ Transit’s Hudson-Bergen Light Rail and Conrail’s Industrial Track. During these periods, NJ Transit Light Rail service between 34th Street Station in Bayonne and Danforth Avenue Station in Jersey City will be maintained via NJ Transit bus service.
Route 440 and Pulaski Street Intersection / Jughandle
  • Ramp roadway construction continues.
  • Median barrier construction on Route 440 continues.
  • Ramp structure construction to southbound Route 440 continues.
  • During the week of 04/24/17, northbound Route 440 traffic will be shifted left (two northbound lanes adjacent to median) and a work zone will be established on the right.
Ramp Area East of Route 440
  • New ramp construction continues.
  • Retaining wall construction continues.
  • Bridge deck construction on the bridge structure over Pulaski Street continues.
  • Roadway construction continues.

03/31/17: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • Reconstruction of Toll Lanes 8-10 continues.
  • During the weekend of 04/07/17, Toll Lanes 8, 9 & 10 will be reopened.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • Widening construction on the ramps to and from the westbound and eastbound HCE is complete to the extent possible and the final alignment has been implemented. Asphalt resurfacing of the ramps will be performed in 2017.
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the Spring of 2017. This work will be supported by Jersey City and Bayonne Police as needed.
Avenue E / Proposed Roundabout
  • New roadway construction on Avenue E near 53rd Street continues.
  • Deep bridge foundation construction in dedicated work zones continues. This work will be supported by Bayonne Police as needed.
  • New bridge pier construction in dedicated work zones continues.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
Route 440 and Pulaski Street Intersection / Jughandle
  • Ramp roadway construction continues.
  • Median barrier construction on Route 440 continues.
  • Ramp structure construction to southbound Route 440 continues.
  • During the week of 04/17/17, northbound Route 440 traffic will be shifted left (two northbound lanes adjacent to median) and a work zone will be established on the right.

Ramp Area East of Route 440
  • New ramp construction continues.
  • Retaining wall construction continues.
  • Bridge deck construction on the bridge structure over Pulaski Street continues.
  • Roadway construction continues.

03/24/17: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • Reconstruction of Toll Lanes 8-10 continues.
  • During the weekend of 04/07/17, Toll Lanes 8, 9 & 10 will be reopened.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • Widening construction on the ramps to and from the westbound and eastbound HCE is complete to the extent possible and the final alignment has been implemented. Asphalt resurfacing of the ramps will be performed in 2017.
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the Spring of 2017. This work will be supported by Jersey City and Bayonne Police as needed.
Avenue E / Proposed Roundabout
  • New roadway construction on Avenue E near 53rd Street continues.
  • Deep bridge foundation construction in dedicated work zones continues. This work will be supported by Bayonne Police as needed.
  • New bridge pier construction in dedicated work zones continues.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
Route 440 and Pulaski Street Intersection / Jughandle
  • Ramp roadway construction continues.
  • Median barrier construction on Route 440 continues.
  • Ramp structure construction to southbound Route 440 continues.
  • During the week of 04/17/17, northbound Route 440 traffic will be shifted left (two northbound lanes adjacent to median) and a work zone will be established on the right.
Ramp Area East of Route 440
  • New ramp construction continues.
  • Retaining wall construction continues.
  • Bridge deck construction on the bridge structure over Pulaski Street continues.

03/17/17: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • Reconstruction of Toll Lanes 8-10 continues.
  • A new traffic pattern was implemented at the Toll Plaza on 2/10/17. Please CLICK HERE for graphic.
  • On Saturday 03/18/17, from 6:30AM to 2:30PM, rehabilitation work within the Toll Plaza area will be performed in a dedicated work zone. There will be no lane closures associated with this work. Please note that lane designations for cash and EZ Pass may be temporarily adjusted to prevent delays.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • Widening construction on the ramps to and from the westbound and eastbound HCE is complete to the extent possible and the final alignment has been implemented. Asphalt resurfacing of the ramps will be performed in 2017.
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the Spring of 2017. This work will be supported by Jersey City and Bayonne Police as needed.
Avenue E / Proposed Roundabout
  • New roadway construction on Avenue E near 53rd Street continues.
  • Deep bridge foundation construction in dedicated work zones continues. This work will be supported by Bayonne Police as needed.
  • New bridge pier construction in dedicated work zones continues.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
Route 440 and Pulaski Street Intersection / Jughandle
  • Ramp roadway construction continues.
  • Median barrier construction on Route 440 continues.
  • Ramp structure construction to southbound Route 440 continues.
Ramp Area East of Route 440
  • New ramp construction continues.
  • Retaining wall construction continues.
  • Bridge deck construction on the bridge structure over Pulaski Street continues.