04/20/18: Construction Update

The following work is scheduled over the next three weeks:
Toll Plaza
  • East side (entering the Turnpike) renovation of existing Toll Utility Building continues.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • No work planned.
Avenue E / Proposed Roundabout
  • During the week of 04/23/18, daytime lane closures will be utilized for pavement striping work between 53rd Street and 50th Street. This work will be supported by Bayonne Police.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited.
Route 440 and Pulaski Street Intersection / Jughandle
  • Continue traffic signal construction on Route 440.
  • During the week of 04/23/18, nighttime paving work will be performed on Route 440. Nighttime traffic shifts and temporary detours will be utilized to accomplish the work. This work will be supported by Bayonne Police.
Ramp Area East of Route 440
  • Continue traffic signal construction on Port Jersey Boulevard.
  • During the week of 04/23/18, nighttime asphalt paving work will be performed on the new ramps and roadways to and from Route 440, Pulaski Street and Chosin Few Way. Nighttime traffic shifts and temporary detours will be used to accomplish the work. This work will be supported by Bayonne Police.
Posted in Construction News.